Quail Creek Tributary Drainage
February 2016 - Project Update


     February 2016 activities:
  • Drainage channel grading completed.
  • Slopes at drainage channel completed with top soil, seeding, erosion control matting and final hydro-mulch seeding. 
  • Pilot channel completed.
  • Drainage rock/drop structure completed.
  • Anti-graffiti painting of bridge completed.
  • Low water culvert crossing completed.
     
    Planned activities for the next 3+ weeks:
  • Final hydro-mulch seeding at remaining concrete flumes.
  • Haul away material and debris.





Completed side slopes w/erosion control matting and grass




Drop structure at drainage channel completed



Completed drainage channel looking from loop 410 access road





Completed drainage channel looking from loop 410 access road





Barrington St. bridge

      
If you have questions about the project, please contact:
  
Joey Doctor | Capital Projects Officer
210.207.8415 | joe.doctor@sanantonio.gov 
  
 Visit us at:

Transportation & Capital Improvements (TCI)
PO Box 839966
San Antonio, Texas 78283-3966
210.207.8022


This email was sent to txtravelers@gmail.com by tciinfo@sanantonio.gov |  

Transportation & Capital Improvements
| PO Box 839966 | San Antonio | TX | 78283-3966


No comments:

Post a Comment